Fagen has their break tent built. They continue to move equipment onsite.
Cold weather continues. Weather forecast is predicting it to warm up into the 30’s during the day starting next week which is good news.
The plant process area dirt work is complete, grains areas to be completed by the second week in March. Tank farm and water treatment areas to be finished at the beginning of March. Loiseau will be onsite next week to finish phase I dirt work.
Thorstad to mobilize and start the DDG building pits the first part of March. The grains areas will follow – total grains receiving areas estimated completion in February 2008.
All plant roads are up to grade with gravel.
The rail portion of the dirt work will start this spring.