Construction and Photo Update

Click here for AE's Groundbreaking ceremony.

February 28, 2008

Hoop tent storage building
Footings for west wall of wet cake pad
Energy Center roofing being installed above dryer A and B
Distillation columns
B&B installing the wet well
B&B crew installing force main
installing flour conveyor from hammer mills

 

Aberdeen Energy Construction Update (2/29/08)
We are still on track for a May 2008 start up in lieu of the severe cold weather we have had this year. Fagen, Inc our builder continues to work 7 days week and we have a total of 270 workers on site to date. The Process Building is 98% enclosed with steel siding. The wetcake pad is under construction. The Energy Center is 60% complete and R&R Contracting has about 75% of the rail loop complete with a final completion date of mid March. Piping in Process and Fermentation areas continues. Fagen has began insulating process tanks and piping and  B&B Contracting are installing the force main and wet well for the plant effluent water discharge. GLE has been sponsoring a monthly cookout with the most recent one on February 13 for the construction employees. These cookouts are much appreciated with the cold weather. The cooling tower is almost complete with the exception of pumps and piping. Dry wall is installed in the offices, lab, control, etc in the process building.

February 22, 2008

Mole sieve platforms being installed
Energy Center conveyors
Biomethanator being insulated

 

February 14, 2008

Looking NW from 370 Avenue
Looking north from 370th Ave.
Looking NE from 370th Ave.
Rail work west of grains receiving building
Process building SW corner
Grains receiving
Wet cake pad wall
Energy Center
Energy Center-DDG cooling drum
Ease end of Process looking at maintenance doors
Centrate tank and piping
Bio methanator tanks being insulated

 

February 6, 2008

Water treatment building
TO stack set in place
Southwest side of Energy Center
South MCC Energy Center
Looking at east side of Process Building outside maintenance area
Footings for wetcake pad
East side of Process Building

 

 