Construction and Photo Update
Click here for AE's Groundbreaking ceremony.
February 28, 2008
|
|
|
Hoop tent storage building |
Footings for west wall of wet cake pad |
Energy Center roofing being installed above dryer A and B |
|
|
|
Distillation columns |
B&B installing the wet well |
|
|
|
B&B crew installing force main |
installing flour conveyor from hammer mills |
Aberdeen Energy Construction Update (2/29/08)
We are still on track for a May 2008 start up in lieu of the severe cold weather we have had this year. Fagen, Inc our builder continues to work 7 days week and we have a total of 270 workers on site to date. The Process Building is 98% enclosed with steel siding. The wetcake pad is under construction. The Energy Center is 60% complete and R&R Contracting has about 75% of the rail loop complete with a final completion date of mid March. Piping in Process and Fermentation areas continues. Fagen has began insulating process tanks and piping and B&B Contracting are installing the force main and wet well for the plant effluent water discharge. GLE has been sponsoring a monthly cookout with the most recent one on February 13 for the construction employees. These cookouts are much appreciated with the cold weather. The cooling tower is almost complete with the exception of pumps and piping. Dry wall is installed in the offices, lab, control, etc in the process building.
February 22, 2008
|
|
|
Mole sieve platforms being installed |
Energy Center conveyors |
Biomethanator being insulated |
February 14, 2008
|
|
|
Looking NW from 370 Avenue |
Looking north from 370th Ave. |
Looking NE from 370th Ave. |
|
|
|
Rail work west of grains receiving building |
Process building SW corner |
|
|
|
Grains receiving |
Wet cake pad wall |
Energy Center |
|
|
|
Energy Center-DDG cooling drum |
Ease end of Process looking at maintenance doors |
Centrate tank and piping |
|
|
|
|
Bio methanator tanks being insulated |
|
February 6, 2008
|
|
|
Water treatment building |
TO stack set in place |
|
|
|
Southwest side of Energy Center |
South MCC Energy Center |
Looking at east side of Process Building outside maintenance area |
|
|
|
Footings for wetcake pad |
East side of Process Building |
|
|
|