Photo Gallery
March 2007
-
Fagen has their break tent is finished. One fermenter ring wall is poured; the beer well footings are being poured.
-
Phone and internet are up and operational to Fagen office trailers.
-
Web cam is onsite.
-
All temporary electrical is complete.
-
The plant process area is complete, DDG building to be completed by mid March.
-
Thorstad to mobilize and start the DDG building by mid March.
-
All plant roads are up to grade with gravel, complete.
March 13, 2007
|
|
|
Fermentation ring wall and beer well being formed
|
Looking at beer well, fermentation ring wall and Fagen offices
|
Tank farm Phase I dirt work - pit run
|
|
|
|
Tank farm Phase I dirt work
|
|
Trucks hauling pit run into tank farm
|
March 6, 2007
|
|